| Case StudyModelling the replacement of degraded concrete on the Terra Nitram
            prill tower
              
                Complex concrete refurbishment work
                Global modelling of tower to assess areas of high stress
                concentrations
                Local modelling of staged construction analysis using 'Birth and
                Death' elements 
              
                
                  | The Severnside prill tower
                    was operated by Terra Nitrogen (UK) Ltd to manufacture ammonium nitrate fertiliser. Despite
            a history of regular maintenance and repair, parts of the reinforced concrete structure
            deteriorated over the years due to the severe operating environment,
                    and eventually significant structural repairs were required. ABB formulated an outline repair strategy
            and design and technology consultants Taylor
            Woodrow were appointed undertake the complete project management including the design
            and supervision of the remedial works. Taylor Woodrow chose to use LUSAS Civil &
            Structural to assist with the complex task of modelling the demolition and
            re-construction sequences to replace the degraded concrete in the tower whilst keeping the
            plant operational throughout. History The tower was constructed in 1964. It consists of a 86m high, 15.6m
            diameter drop shaft of 178mm thickness. A five storey reinforced concrete plant house,
            supported on the drop shaft, a lift shaft and a single braced column, forms the upper 75m
            to 100m levels. Despite protective measures being undertaken during its construction a
            number of concrete repairs have had to be made during the towers life.
             | 
 |  Global
            modelling Prior to the detailed staged construction design a LUSAS analysis of the complete
            structure was undertaken for dead, plant, circulation and wind loads to assess the
            structural behaviour of the tower both in its as-built and current deteriorated condition
            for checking with relevant design codes. Fine mesh divisions were used in areas of repair
            and coarse mesh divisions used in areas remote from the plant house.  Results from the as-built model confirmed the behaviour of the structure and identified
            areas where high stresses could be expected. Results from the model incorporating reduced
            modulii of elasticity for all areas of degradation showed how initial as-built forces had
            redistributed due to the ammonium nitrate attack and indicated an even more urgent need
            for the remedial work to be undertaken. This latter analysis also proved extremely useful
            in deriving subsequent repair sequences. In all, over 100m2 of drop shaft wall and damaged
            areas of beams, columns, slabs and walls for a number of levels of the plant house
            required replacing.
            
            The LUSAS birth and death facility The complex sequence of structural repairs was modelled in LUSAS using the birth and
            death facility. This allows elements to be de-activated to simulate areas of concrete
            removal, resulting in stress redistribution in the model. Following repair, the elements
            are re-activated with corresponding new material properties. In this manner a structural
            assessment was undertaken for all stages of the repairs to the tower including the use of
            major temporary works such as support frames, props and jacks to ensure the structure
            remained safe at all times. Modelling of the staged repair sequences While some local patch repairs were necessary at the lowest level of the plant house
            the areas requiring most extensive repairs were between level 5 and the roof at 100m
            level. Each level of the plant house presented different problems and required appropriate
            repair sequences and temporary support arrangements. At each stage of the repair sequence
            the forces in both temporary props and the support frame and the walls, columns, beams and
            floor slabs of the plant house were examined in LUSAS to ensure the structure remained
            safe. For the temporary support frame calculated deflections were compared with on-site
            measurements to ensure nothing unexpected was happening. In general, good correlation was
            achieved confirming the validity of the LUSAS modelling and design calculations. 
 Previous patch repairs to the drop shaft wall had
            indicated that such repairs should be undertaken by a staged replacement of alternate
            panels not exceeding of 1m x 2m in area. However, by using appropriate temporary works
            including jacking, LUSAS confirmed that considerably larger areas could be broken out and
            repaired in a single operation. "Adopting the 'birth and death' technique
            in the LUSAS analyses gave us a high degree of confidence that the structure would remain
            safe at all times. This was of prime importance as the plant had to remain operational
            thoroughout the duration of the repair contract."
              
            Graham Anderson, Taylor Woodrow
        
 Find out more  
  Other LUSAS Civil &
        Structural case studies: |