Case
Study
Share this
article
Mizen Head Footbridge
The new Mizen Head Footbridge is a
reinforced concrete through-arch structure that spans 50m across a
sea gorge to connect the island of Cloghán, at the tip of Mizen
Head, with the mainland in South-west Cork, Republic of Ireland. RPS
Consulting Engineers Ltd. used LUSAS Bridge analysis software to
structurally assess an ageing a bridge that stood at the same
location and to assist with the design and assessment of the effects
of constructing a visually identical new replacement structure in
stages around the original bridge at the same time as it was being
sequentially demolished.
Original Bridge
The original bridge was completed in
1909 for the Commissioners of Irish Lights (CIL) and was used to
provide access for lighthouse keepers and for CIL staff. It
comprised both precast and in-situ reinforced concrete elements and
was the first reinforced concrete bridge to be built in Ireland. Its
span was of a record length for reinforced concrete arch
construction at the time. Since 1994, when public access was given
to the lighthouse buildings, around 50,000 visitors have crossed the bridge
annually.
|
|
Inspection of original Mizen
Head Footbridge |
Structural
elements of the bridge |
Inspection and
Assessment
Whilst the bridge had been regularly
maintained since its construction extreme weather and environmental
conditions slowly took their toll. In 2000 an inspection by CIL
engineers revealed areas of spalled concrete and reinforcement
corrosion. In 2002, CIL appointed RPS (then M.C. O’Sullivan and
Company Ltd.) to conduct a further inspection and in-depth
structural assessment of the footbridge. RPS undertook material
tests, observations and geometrical surveys to help establish the
condition of the structure and to provide material and geometric
parameters for use with maintenance, repair or strengthening scheme
development. Defects noted during the inspections included rust
staining, areas of hollow-sounding concrete, cracking and localised
areas of missing concrete - all relating to corroding reinforcement.
Various non-destructive and destructive tests were carried out on
selected parts of the structure. These involved cover meter and
hammer-tap surveys; chloride content testing; concrete core removal
to derive equivalent cube strengths and for use with petrographic
examinations; and localised breaking-out of concrete in the hangers
to examine the condition of the reinforcement. In summary, very high
chloride content levels were present throughout the structure which,
whilst not affecting the integrity of concrete directly, provided a
mechanism for reinforcement corrosion to occur. Based on the results
it was concluded that the concrete, excluding the concrete in the
cover zone, was of a sound nature.
Modelling and
Analysis
Based on the original construction
drawings and the information gathered during the principal
inspection, RPS carried out a finite element assessment of the
structure using LUSAS. Structural member stiffnesses were calculated
neglecting the cover layer concrete. Structural member resistances
were calculated using half the reinforcement as indicated in the
construction drawings. The results indicated that the structure was
still adequate for continued use due to good reserves of structural
resistance to applied dead and live loading effects. However,
because the central suspended span of the deck was relying on
reinforced concrete hangers in direct tension and there was high
chloride-induced steel corrosion throughout the structure, it was
recommended that the hangers be strengthened and that measures be
taken to halt the corrosion of reinforcement in the structure. A
monitoring regime was set-up on the structure with inspections at
six-monthly intervals.
LUSAS Model of
Original Mizen
Head Footbridge
In 2004, RPS produced a preliminary
report for strengthening the bridge recommending the reinforcement
of hangers with Near Surface Mounted Fibre Reinforced Polymer (NSM
FRP) bars, concrete repairs to repair defects the installation of a
cathodic protection system to stall the rate of reinforcement
corrosion. But subsequent electrical continuity testing of
reinforcement in the structure in 2005 by specialist contractors
showed that there was insufficient general continuity of
reinforcement steel to allow a cathodic protection system to be
used, and as a result the footbridge was closed to pedestrian
traffic. In June 2005, an access scaffold was installed to allow
access to Mizen Head to be maintained until a permanent solution was
developed.
New Mizen Head
Footbridge
After considering a number of total
replacement options, the construction of a new two-pinned concrete
arch bridge with a 120 year design life was eventually chosen. This
client-preferred scheme produced a visual replica of the existing
bridge and had the benefit of a 700mm wider deck. It required the
initial construction of new arch ribs parallel to and outside the existing
ribs, using the existing ribs (which were strengthened as required)
as falsework. The sequential demolition of the existing bridge could
then take place, followed by the construction of new trestles, edge
beams, hangers and deck slab. Existing mass concrete
foundations at the arch springing points and deck ends were
retained, and stainless steel reinforcement was used throughout. A 52m long, temporary steel truss was used to span across
and above the existing bridge deck to provide support to the main
scaffold and act as a fail-safe for the various temporary works.
Construction of new
arch ribs alongside original
Mizen Head Footbridge
showing access scaffold supported from temporary truss.
Modelling and
Analysis
Modelling and analysis for the new
structure was again undertaken using LUSAS with design being carried
out to British Standard BS5400. Live loading consisted of 5kN/m2
nominal pedestrian loading and a maintenance vehicle load case. The
LUSAS model used for designing the new permanent structure was also
a 3D thick beam model, but wider than the old model as the new
structure was built outside the old one. RPS Consulting Engineer
Ltd.’s resident engineer was also one of its design team and had a
LUSAS model running on site to check the old and new bridges for all
stages of construction and demolition process. Kieran Ruane, Technical Director of
RPS Consulting Engineers Ltd. explains: We set up monitoring points
on the old structure and modelled the loading situations as the
temporary works loads came on, followed by the load from the new
arch ribs. Once the new arch ribs were braced, they were used to
support the temporary works and allowed the demolition of the old
bridge." In summary he said: "It was a
very interesting project to have been involved with, not only
because of its complexity, but because of the project’s timescale
we ended up using variations of our LUSAS model for assessment,
design and construction over a period of 10 years.
Open to the Public
New Mizen Head Footbridge opened to
the public on St Patrick’s Day, 17th March 2011. Fáilte Ireland,
the Commissioners of Irish Lights, and Cork County Council jointly
funded the Euro1.8 million rebuilding contract. It was delivered
safely, within budget and stands as testimony to a very successful
collaboration between the client, Cork County Council, the
contractor, Carillion Irishenco Ltd, RB International - the
contractor's construction engineer, and RPS Consulting Engineers
Ltd.
In
the news:
"It
was a very interesting project, not only because of its complexity,
but because of the project timescale we used variations of our
LUSAS model for assessment, design and construction over a period of
10 years."
Kieran Ruane, Technical
Director, RPS Consulting Engineers Ltd.
Share this
article
Find out more
Other LUSAS Bridge case studies:
|