| 
           Case
          Study 
          Widening and
            strengthening of Kingston Bridge
            
              - Multi-span masonry arch bridge
 
              - 2D modelling of new arch structures
 
              - Local transverse analysis to determine forces in spandrel walls
 
             
            
            Detailed inspections of Kingston Bridge in Kingston upon
            Thames, Surrey, revealed numerous defects in the 1914 structure and load assessments
            resulted in vehicles of over 38 tonnes being prohibited from crossing the bridge.  To
            allow strengthening of the bridge for increased loadings a permanent widening scheme was
            chosen to allow traffic flows to be maintained during strengthening works and to help
            reduce the environmental impact during the construction work. It also provided the
            opportunity to introduce permanent facilities for buses and cyclists. Designers Symonds Group Ltd used LUSAS Bridge
            to model the spans of the widened structure for its client the Royal Borough of Kingston. 
          
            
              | The bridge widening adds 6.6 m to the previous
            width of 17.5 m.  New piers comprise reinforced concrete stems founded on a
            reinforced concrete pile cap with bored cast in-situ concrete piles. The piers are faced
            with natural Portland Stone.   Precast concrete arch units were used for
            constructing the spans of the widened bridge to minimise the disruption to river traffic
            during construction. The precast units forming the spans of the widened bridge are made
            continuous over the crown using coupled reinforcing bars with in-situ concrete. These
            precast units are faced with masonry and brick to match the existing arch profile and
            finishes. An in-situ lightweight reinforced concrete saddle is cast on top of the precast
            units to form a composite section. Starter bars project from the extrados of the precast
            units to provide continuity with the saddle.
             | 
              
                  
  | 
             
            
              |   | 
                | 
             
            
              | The spans of the widened bridge
            were analysed using a 2-dimensional LUSAS Bridge model.  Each span was
            idealised as being restrained at each end by the piers. To accommodate shrinkage and
            thermal effects movement joints are incorporated at the end of each arch.  The
            transverse stiffness of the arch was ignored in the analysis. A plane stress analysis of
            unit width was therefore carried out using plane stress elements. In addition the
            stiffening effects of the spandrel walls were not taken into account in the design of the
            composite reinforced concrete arch barrel.  A local transverse analysis was carried
            out to determine the forces in the spandrel walls. End support conditions were
            modelled to simulate the degree of fixity provided during the construction of the bridge
            and also in the permanent situation. The analysis therefore considered the three
            pinned, two pinned and fixed situations.
             | 
              
                  
  | 
             
           
            The superstructure was modelled globally as a five span
            masonry arch using another analysis program. This analysis was used to investigate the out
            of balance forces in the piers and hence to check their stability during the construction
            phases and when strengthening is completed.  The analysis of the lightweight
            reinforced concrete saddle and brick arch composite behaviour was based on a nonlinear
            analysis of the central river span. The material model for the existing brick arches
            assumed no tensile stresses. The reinforced concrete saddle was modelled using linear
            elastic properties based on uncracked section behaviour.  The behaviour of the finite
            element model was benchmarked against a single span model by comparing the order and
            position of hinge formation under a point load positioned close to midspan. 
            For more details of the widening and strengthening project for this
            bridge visit the London Bridges Engineering
            Group website.
              
            
          
          
    Find out more
    
      
     
          
           
          Other LUSAS Bridge case studies:
          
          
          
             
            |